RECENT PROJECTS

RED-E-DUCT Precast Electrical Duct Bank is changing the way underground electrical duct banks are installed. Recent projects demonstrate how RED-E-DUCT saves time and reduces labor requirements, allowing construction teams to complete installations faster at a lower total cost.
LNG PRODUCTION AND EXPORT FACILITY
Oil, Gas & Chemical
recent_lng_standards_stubups2

More than 4,500 Standard and Stub Up RED-E-DUCT sections were produced, delivered and installed in record time. The installation contractor realized a significant reduction in the labor required to install and complete the buried conduit system.  Precast duct bank was installed and backfilled throughout the project site enabling other work activity to begin earlier than if conventional cast-in-place construction methods would have been used.

PAPER PACKAGING MILL
Industrial
recent_paper_standards_stubups

Using a trench box and a backhoe, the project team installed sixteen conduit joints in a 4High x 4Wide RED-E-DUCT, nearly 160 feet of conduit in full concrete encasement, in less than two minutes.  The RED-E-DUCT installation occurred in January with an average daily high temperature of 24oF.  If conventional cast in place construction methods would have been used, the underground construction work would have taken much longer to complete and at significant additional expense to the Owner.  

1,182MW COMBINED-CYCLE POWER PLANT
Power Generation
recent_1182mw_standards_stubups

RED-E-DUCT assisted the project team with overcoming local craft labor shortages and an aggressive completion schedule.  Schedule and cost savings resulting from the use of the precast duct bank exceeded the client’s expectations.  Contech was recognized by the contractor as a key contributing supplier and presented an award for exceptional new product and performance.

OIL REFINERY, CA
Oil, Gas & Chemical
recent_chevron_standards_stubups

Plant equipment retrofits requiring traditional underground duct bank construction significantly disrupt normal facility operation resulting in loss of production and revenue.  Chevron and the design/construction team selected RED-E-DUCT to construct duct banks which will significantly reduce the impact of construction on facility operations. Additionally, on-site safe working conditions improve as fewer workers are required with less time required in confined trenches.  

730MW COMBINED-CYCLE POWER PLANT, WI
Power Generation
recent_allient_standards_stubups

RED-E-DUCT was selected to accelerate underground duct bank construction and project planners were not disappointed. A four-man crew routinely installed 4,000 feet of 4 inch conduit encased in precast concrete in an eight-hour shift.   Horizontal and vertical duct bank runs were installed using a combination of RED-E-DUCT Standards and Stub-ups.

ETHANE CRACKER/PETROCHEMICAL FACILITY, TX
Oil, Gas & Chemical
recent_exxon_standards_stubups

RED-E-DUCT was installed under and alongside site access roads in multiple locations. Precast Duct Bank became an ideal solution where site conditions required managing a high-water table and demanded rapid installation to ensure road closures and site disruptions were kept to an absolute minimum.  

CEMENT PRODUCTION FACILITY, SD
INDUSTRIAL
recent_cement_standards_stubups

RED-E-DUCT Precast Duct Bank was used in a side-by-side configuration to minimize equipment downtime, enabling the installation crew to  complete the project within a tightly defined construction timeline.

MINNESOTA POWER, MN
POWER TRANSMISSION & DISTRIBUTION
recent_minnesota_standards_stubups

Installed directly in front of a bank entrance, RED-E-DUCT was used in place of portions of cast-in-place duct bank to significantly reduce construction time. The speed of installation successfully reduced traffic disruptions and the impact to local businesses.

MALMSTROM AIR FORCE BASE, MT
Government, Military & Municipal
recent_malstrom_standards_stubups

Installation occurred in a single shift to cross the only access road into the military base. Maintaining traffic flow in and out of the facility was of utmost importance with minimal impact to ongoing military operations.

CHEMICAL PLANT, TX
INDUSTRIAL
recent_chemical_standards_stubups

The chemical plant required a new utility line, designed to run directly under railroad tracks that provide feedstock delivery to the plant.   A prolonged installation would force a temporary shut-down of the facility until the work completed.  With RED-E-DUCT, the contractor will install the underground duct bank and backfill immediately permitting the facility to quickly resume normal operations.   In addition, RED-E-DUCT ability to carry significant loads, permitted the designer to reduce the bury depth by two feet, further reducing construction costs.

EAST NEUSE PUMP STATION, NC
Government, Military & Municipal
recent_east_standards_stubups

Installation of a new utility corridor under the East Neuse River required the installing contractor to construct a temporary damn and re-route the water flow during construction. The design and installation team selected RED-E-DUCT to quickly install and backfill the duct bank which will shorten the number of days required to divert the water flow.  In addition to the time savings, project risk was reduced, and safe working conditions improved.

RED ROCK DAM, IA
Government, Military & Municipal
recent_red_standards_stubups

The Contractor awarded the work faced a challenge of installing twin 2High x 2Wide duct bank on an embankment at a 30-degree slope.  Selecting and installing  RED-E-DUCT significantly reduced the complexity and time required to complete the work.  The use of precast duct bank eliminated the need for multiple concrete pours and pumping rigs which would have been required had conventional cast in place construction methods been used.

We bring quality ideas to every project.  As the leading supplier of precast electrical duct bank products in the U.S., we consistently deliver customized solutions and unrivaled expertise, all backed by years of research, engineering, testing and development.

FIND OUT IF RED-E-DUCT IS RIGHT FOR YOUR NEXT PROJECT

Schedule an appointment

1

Power Transmission & Distribution

Duct Bank Installation 

Installed in front of a bank entrance, RED-E-DUCT was used in
conjunction with cast-in-place duct bank to significantly reduce
construction time. Speed of installation reduced the impact to
local businesses.

Power Transmission & Distribution

Duct Bank Installation 

RED-E-DUCT Precast Duct Bank was utilized to reduce overall site construction time. A crew of four was able to install 60 feet of linear duct bank per hour. Horizontal and vertical runs were installed, including precast Stub-Ups containing rigid galvanized conduits.

Industrial Facility

Duct Bank for Fiber and Power Cable

RED-E-DUCT Precast Electrical Duct Bank was used to carry fiber and power cables serving a water treatment plant, significantly reducing the time and cost of installation.

Oil, Gas & Chemical

Duct Bank Infrastructure Under Access Roads   

RED-E-DUCT Precast Duct Banks were installed under and alongside site access roads in multiple locations. RED-E-DUCT became a perfect solution where site conditions required managing a high-water table and rapid installation, ensuring road closures and site disruptions were kept to a minimum.